If you have pre-customised this work section using the "questions and answers" provided as part of the downloading process, it may be necessary to amend some clauses to suit the final project-specific version.
The section must still be checked and customised to suit the project being specified, by removing any other irrelevant details and adding project-specific details and selections.
This section relates to the supply and laying of Marley New Zealand Limited above ground gravity flow PVC-U sanitary systems for residential and commercial applications.
It includes:
Modify or extend the above description to suit the project being specified.
Written for a combined foul and grey water.
Some industrial effluent may need to be specified separately.
Provide additional project-specific clauses for specialty installations (healthcare facilities).
This section does not cover vacuum drainage systems, seek specialist advice if required.
Note; This section (without Q&A) is written to allow the use of either NZBC G13/AS1 or NZBC G13/AS3. NZBC G13/AS3 allows the use of AS/NZS 3500.2: 2018 (modified) as an Acceptable Solution. For buildings/systems over 3 storeys and/or specialised systems (ie. hospitals, labs etc) NZBC G13/AS3 (or NZBC G13 VM1) must be used.
Note: Residential applications include light commercial projects
Refer to 7151 SANITARY FIXTURES, TAPWARE & ACCESSORIES for sanitary fixtures.
Refer to 7123 HOT AND COLD WATER SYSTEM for potable water systems.
Refer to 7420MD MARLEY DBLUE® ACOUSTIC SANITARY SYSTEM for acoustic sanitary system.
Refer to 7142 GREYWATER SYSTEMS for greywater systems.
Include cross references to other sections where these contain related work.
Refer to electrical sections if electrical pan vents or pumps are used.
Refer to the general section 1232 INTERPRETATION & DEFINITIONS for abbreviations and definitions used throughout the specification.
The following abbreviations apply specifically to this section:
DWV | Drain, Waste and Vent |
Refer to the general section 1233 REFERENCED DOCUMENTS. The following documents are specifically referred to in this section:
NZBC G1/AS1 | Personal hygiene |
NZBC G13/AS1 | Foul water - Sanitary plumbing |
NZBC G13/AS3 | Foul water - Sanitary plumbing and drainage |
AS 2887 | Plastic waste fittings |
PVC-U pipes and fittings for drain, waste and vent applications | |
AS/NZS 1462.22 | Methods for test for plastic pipes and fittings - Method 22: Method for determination of pipe stiffness |
AS/NZS 1462.3 | Methods for test for plastic pipes and fittings - Method for determining the impact characteristics of pipes |
Installation of PVC pipe systems | |
AS/NZS 3500.2: 2018 | Plumbing and drainage - Sanitary plumbing and drainage |
Delete from the DOCUMENTS clause any document not cited. List any additional cited documents.
This section uses AS/NZS 3500.2: 2018 despite being superseded by AS/NZS 3500.2: 2021. Because AS/NZS 3500.2: 2018 is cited in NZBC G13/AS1 - AS3. At the time of writing, AS/NZS 3500.2: 2021 is not cited and is therefore an Alternative Solution.
The following are related documents and if referred to in the work section need to be added to the list of DOCUMENTS
NZBC G12/AS1 | Water supplies |
Plumbing and drainage - Glossary of terms | |
Plumbing and drainage - Housing installation | |
BRANZ BU 364 | Preventing noise in plumbing installations |
Manufacturer and supplier documents relating to this part of the work:
Marley OPTIM® DWV Technical Design Manual
Marley Material Safety Data Sheets
List documents relating to this part of the work, i.e. technical product/system specifications, test reports, appraisals, certification, etc. Normally they will be referred to in the text by the abbreviated title.
Manufacturer/supplier contact details
Company: | Marley New Zealand Limited |
Web: | |
Email: | guyy@marley.co.nz |
Telephone: | 09 279 2799 |
It is important to ensure that all personnel on site have access to accurate, up to date technical information on the many products, materials and equipment used on a project. In most cases individual products are not used in isolation, but form part of a building process. Also a particular manufacturer's and/or supplier's requirements for handling, storage, preparation, installation, finishing and protection of their product can vary from what might be considered the norm. Access to technical information can help overcome this potential problem.
Provide an installer warranty:
2 years: | For installation |
Refer to the general section 1237 WARRANTIES for additional requirements.
Modify or expand the clause to suit project or installer requirements, options include:
Plumbers to be experienced competent workers, familiar with the materials and the techniques specified. Carry out all work under the direct supervision of a certifying plumber under the Plumbers, Gasfitters and Drainlayers Act 2006.
Substitutions are not permitted to any of the specified systems, components and associated products listed in this section.
~
It is sometimes necessary to call for diagrammatic pipework layouts from the plumber prior to installation. This will depend on the degree of detail provided elsewhere and on whether to some degree at least the design of the system is a contract requirement.
Provide the following general operation and maintenance information as electronic PDF format documents:
~
Use this clause to list requirements of information that is required but which does not warrant a separate specialist operation and maintenance manual. Amend the clause if hard copy documents are required.
Provide this information prior to practical completion.
The general section 1234 DOCUMENTATION describes the process of as built documentation. Modify the PROVIDE OPERATION AND MAINTENANCE INSTRUCTIONS clause in that section to describe the general project requirements if necessary.
Refer to the general section 1238 AS BUILT DOCUMENTATION for the requirements for submission and review of as built documents and records.
Provide the following as built documents and records:
~
The general section 1238 AS BUILT DOCUMENTATION (or 1234 DOCUMENTATION if not available) describes the process of submission and review of as built documentation. Use this clause to describe the specific requirements of what the required as built documents are to include.
Provide the following compliance documentation: -
List the Producer Statements - Construction (PS3) required from installers that are required as a condition of carrying out this work.
List also Producer Statements - Construction Review (PS4) required from consultants to be engaged by the Contractor.
Producer Statement - Design (PS1), may be required where certain design work is undertaken by the Contractor or manufacturer / importer / distributor.
Confirm timing before carrying out any tests. Supply potable water and apparatus needed. Test to NZBC G13/AS1 or AS/NZS 3500.2: 2018, 15 as required. Carry out and record a visual inspection that each joint showed no evidence of leaks.
Marley PVC-U DWV pipework comprised of unplasticised PVC waste pipes, traps and fittings manufactured to AS/NZS 1260, tested to AS/NZS 1462.22 and AS/NZS 1462.3, and compliant with AS/NZS 3500.2: 2018. Available in a range of pipe types with nominal size DN20 to DN150 and stiffness class SN4 and SN6. Refer to SELECTIONS for options.
Marley PVC-U DWV pipework comprised of unplasticised PVC waste pipes, traps and fittings manufactured to AS/NZS 1260, tested to AS/NZS 1462.22 and AS/NZS 1462.3, and compliant with AS/NZS 3500.2: 2018. Available in a range of pipe types with nominal size DN 100 to DN 375 and stiffness class SN8 and SN10. Refer to SELECTIONS for options.
Marley PVC-U vent pipes comprised of unplasticised PVC including fittings and accessories manufactured to AS/NZS 1260, tested to AS/NZS 1462.22 and AS/NZS 1462.3, and compliant with AS/NZS 3500.2: 2018. Available in a range of pipe types with nominal size DN 40 to DN 100 and stiffness class SN4 to SN10. Refer to SELECTIONS for options.
To AS 2887. White polybutylene or PVC or chromed plastic exposed pipes, traps and wastes, including all associated fittings, refer to SELECTIONS.
Other than PVC-U
To AS/NZS 3500.2: 2018. Satin chrome plated exposed pipes, traps and wastes including all associated fittings refer to SELECTIONS.
Marley Optim® DWV assembly to AS/NZS 3500.2: 2018, comprised of:
- Gully trap comprising (2x DN40mm inlets; 1x DN50mm inlet; 1x DN65mm outlet). Gully trap size 199mm high x DN100mm socket width.
- Siphon insert with O-ring
- OPTIM® 100mm DWV pipe - offcut to fit
- Marley leak control floor flange - 126.100.LC100
- Floor waste option A - Flange with Stainless Steel Grate - TFW100RS
- Floor waste option B - Vinyl Rite Floor Waste System - VR100SS
Refer to SELECTIONS.
Modify clause to suit project requirements
Vinyl Rite Floor Waste System, with solvent joint and standard white PVC grate. Available in a range sizes and grate types, refer to SELECTIONS for options.
Refer to 7461 FOUL WATER DRAINAGE for gully traps.
Plasticised PVC tape system with primer, mastic fixing and outer coating.
Fire rated sealer and associated fire retardant strip, fire resistant collars and fire resistant moulded mineral fibre refractory panels, to the manufacturer's requirements.
Sealers used for caulking the hole around the pipe, foam sealer for slots accommodating several pipes, and strip for plastic plumbing services.
Clause suitable for residential and light commercial, for larger commercial projects refer to 7382 FIRE STOPPING SYSTEMS.
Carry out this work to NZBC G13/AS1 and NZBC G1/AS1 and complete all tests to G13/AS1, 7.1 Test Methods.
Delete this clause if using AS/NZS 3500.2: 2018 / NZBC G13/AS3.
Carry out this work to AS/NZS 3500.2: 2018, as modified by NZBC G12/AS3, and complete all tests to AS/NZS 3500.2: 2018, 15 Testing of Sanitary Plumbing and Sanitary Drainage Installations.
Delete this clause if using NZBC G13/AS1.
Avoid electrolytic action by eliminating actual contact or continuity of water between dissimilar metals.
Extend this clause where particular project issues justify additional information and guidance
Handle and store pipes, fittings and accessories to avoid damage. Store on site under cover on a clean level area, stacked to eliminate movement and away from work in progress.
Set out location of all stacks, discharge pipes, fittings and vent pipes and the completeness of their discharge into the drainage system.
Fit core holes and sleeves as needed throughout the structure in conjunction with the boxing, reinforcing and placing of concrete. Sleeve diameter to be 25mm larger than outside diameter of pipe accommodated. Strip core holes and make good after installation of pipework.
Fit and fix stacks, wastes and pipes in ducts independent of all other services so they are easily replaceable for their full length. Wrap or tape pipes buried in concrete.
Fit and fix traps and wastes to enable access for cleaning and for maintaining the total system.
Unless the location and height are clearly delineated on the drawings, confirm installation height and plan locations of sanitary fittings before commencing the piping installation.
Separate metals subject to electrolytic action from each other and from treated timber, concrete and other lime substances by space, painting of surfaces, taping, or separator strips.
Conceal traps and wastes in the fabric of the building in accordance with manufacturer requirements.
Fit and fix white polybutylene or PVC or chromed plastic exposed pipes, traps and wastes, including all associated fittings in accordance with manufacturer requirements.
Fit and fix satin chrome plated exposed pipes, traps and wastes in accordance with manufacturer requirements.
Refer to 7461 FOUL WATER DRAINAGE for installation of gully traps.
Prime and solvent weld joints using spigots and sockets to Marley requirements.
Jointing to be in accordance with Marley OPTIM DWV jointing procedures as shown in the Marley OPTIM technical manual.
Used for smaller pipe sizes up to and including DN175.
Install flanged joints and seal ring compression joints to Marley requirements.
Jointing to be in accordance with Marley OPTIM DWV jointing procedures as shown in the Marley OPTIM technical manual.
Used for pipe sizes 100DN and greater.
Accommodate longitudinal movement in pipes resulting from temperature changes. Incorporate expansion joints in PVC-U pipes. Install PVC pipes to AS/NZS 2032. Take particular care to allow for movement at horizontal take-off locations from stacks.
Size traps and pipes as required for each fixture or appliance. Establish the developed length of waste pipes. Vent and allow access for cleaning as required. Follow the most direct line with the least number of bends to NZBC G13/AS1: Foul water sanitary plumbing, table 4, Discharge unit loading for stacks and graded discharge pipes and table 7, Distance between supports.
Delete this clause if using AS/NZS 3500.2: 2018 / NZBC G13/AS3.
Size traps and pipes as required for each fixture or appliance. Establish the developed length of waste pipes. Vent and allow access for cleaning as required. Follow the most direct line with the least number of bends to AS/NZS 3500.2: 2018, table 3.3.1, for fixture loading and AS/NZS 3500.2: 2018, table 10.2.1, distance between supports.
Delete this clause if using NZBC G13/AS1.
Size stacks and vents to NZBC G13/AS1: Foul water sanitary plumbing, table 2, Fixture discharge pipe sizes and discharge units and table 6, Vent pipe sizes. Extend up past the highest branch to form a discharge stack vent terminating to NZBC G13/AS1: Foul water sanitary plumbing, figure 12 and finishing at the base with a 45 degree bend. Support system to NZBC G13/AS1: Foul water sanitary plumbing, table 7, Distances between supports.
Delete this clause if using AS/NZS 3500.2: 2018 / NZBC G13/AS3.
Size stacks and vents to AS/NZS 3500.2: 2018, table 6.3(A), for fixture discharge pipe sizes and discharge units and AS/NZS 3500.2: 2018, table 3.9.3.1, vent pipe sizes. Extend up past the highest branch to form a discharge stack vent terminating to AS/NZS 3500.2: 2018, section 6.9 Vents, and finishing at the base with a 45 degree bend. Support system to AS/NZS 3500.2: 2018, table 10.2.1, for distances between supports.
For fully vented or single stack systems, extend venting requirements using AS/NZS 3500.2: 2018, section 8 for Fully Vented Systems or AS/NZS 3500.2: 2018, section 9 for Single Stack Systems.
Delete this clause if using NZBC G13/AS1.
Size pipes as required for each urinal. Establish developed length of waste pipes, vent as required, and allow access for cleaning. Follow the most direct line with the least number of bends to NZBC G13/AS1: Foul water sanitary plumbing, table 4, Discharge unit loading for stacks and graded discharge pipes and to NZBC G13/AS1 table 7, Distances between supports.
Waterless urinals must be connected directly to PVC, not to copper or brass, as undiluted urine may corrode copper or brass pipe.
Delete this clause if using AS/NZS 3500.2: 2018 / NZBC G13/AS3.
Size PVC-U pipes as required for each urinal. Establish developed length of waste pipes, vent as required, and allow access for cleaning. Follow the most direct line with the least number of bends to AS/NZS 3500.2: 2018, table 3.3.1, fixture loading and AS/NZS 3500.2: 2018, table 10.2.1, for distances between supports.
Note: Do not connect to copper or brass, pipes and fittings.
Waterless urinals must be connected directly to PVC, not to copper or brass, as undiluted urine may corrode copper or brass pipe.
Delete this clause if using AS/NZS 3500.2: 2018 / NZBC G13/AS3.
Install fire resistant, sealers, strips, collars and panels in accordance with the fire retardant manufacturer requirements.
Clause suitable for residential and light commercial, for large commercial projects refer to 7382 FIRE STOPPING SYSTEMS.
Carry out routine trade cleaning of this part of the work including periodic removal of all debris, unused materials and elements from the site.
Use this standard generic clause and add additional specific requirements.
ESD note: Re-cycling is addressed in the general section WASTE MANAGEMENT; amend this clause if it is to apply to this section.
Repair damaged or marked elements. Replace damaged or marked elements where repair is not possible or will not be acceptable.
Use this standard generic clause and add additional specific requirements.
Pre-test all pipework during construction. On completion of the work and before approval for acceptance of the pipework, carry out a final test to the approval of the engineer and if required witnessed by the representative of the territorial authority.
For further details on selections go to www.marley.co.nz
Substitutions are not permitted to the following, unless stated otherwise.
If substitutions are permitted modify the statement above, ensure the NO SUBSTITUTIONS clause from GENERAL is treated the same.
Select the options to suit the project and delete options not specified.
Location: | ~ |
Manufacturer: | Marley New Zealand Limited |
Pipe brand/type: | Marley~ |
Pipe diameter: | ~ |
Jointing: | ~ |
Stiffness class: | ~ |
Fittings: | Marley~ |
Options:
Pipe brand/type: | Marley Optim |
Pipe diameter: | 20mm, 32mm, 40mm, 50mm, 65mm, 80mm, 100mm, 150mm |
Jointing: | Solvent joint (for smaller pipe sizes up to and including DN175) or Rubber ring joint (for pipe sizes 100DN and greater) |
Stiffness class: | SN4, SN6 |
Fittings: | Refer to Marley DWV Technical Design Manual for information on product range |
Location: | ~ |
Manufacturer: | Marley New Zealand Limited |
Pipe brand/type: | Marley~ |
Pipe diameter: | ~ |
Jointing: | ~ |
Stiffness class: | ~ |
Fittings: | Marley~ |
Options:
Pipe brand/type: | Marley Optim |
Pipe diameter: | 20mm, 32mm, 40mm, 50mm, 65mm, 80mm, 100mm, 150mm, 175mm, 225mm, 300mm, 375mm |
Jointing: | Solvent joint (for smaller pipe sizes up to and including DN175) or Rubber ring joint (for pipe sizes 100DN and greater) |
Stiffness class: | SN4, SN6, SN8, SN10 |
Fittings: | Refer to Marley DWV Technical Design Manual for information on product range |
Location: | ~ |
Manufacturer: | Marley New Zealand Limited |
Pipe brand/type: | Marley~ |
Pipe diameter: | ~ |
Jointing: | ~ |
Stiffness class: | ~ |
Fittings: | Marley~ |
Options:
Pipe brand/type: | Marley Optim |
Pipe diameter: | 40mm, 50mm, 65mm, 80mm, 100mm |
Jointing: | Solvent joint (for smaller pipe sizes up to and including DN100) or Rubber ring joint (for pipe size 100DN) |
Stiffness class: | SN4, SN6, SN8, SN10 |
Fittings: | Refer to Marley DWV Technical Design Manual for information on product range |
Location: | ~ |
Manufacturer: | ~ |
Brand: | ~ |
Material/type: | ~ |
Options:
Material/type: | White polybutylene, PVC or chromed plastic |
Location: | ~ |
Manufacturer: | ~ |
Brand: | ~ |
Material/type: | Satin chrome plated |
Location: | ~ |
Manufacturer: | Marley New Zealand Limited |
Brand: | Vinyl Rite Floor Waste System |
Joint: | Solvent joint |
Grate: | ~ |
Options:
Grate: | Chrome plated brass 100DN-VR100CP, Chrome plated brass 80DN-VR80CP, Stainless steel round 100DN-VR100SS, Stainless steel round 80DN-VR80SS, White PVC 100DN-VR100WH, White PVC 80DN-VR80WH |
Location: | ~ |
Manufacturer: | Marley New Zealand Limited |
Brand: | Marley Optim® DWV |
Product Code: | COMP.100.50.40 |
Trap insert: | Syphon insert with O-ring |
Flange adapter: | OPTIM® DWV pipe - offcut to fit |
Floor flange: | Leak control floor flange - 126.100.LC100 |
Floor wastes: | ~ |
Options:
Floor wastes: | TFW100RS - Flange with Stainless Steel Grate |
| VR100SS - Vinyl Rite Floor Waste System |
NOTE - 4-way boss diameters are 2x DN40mm inlets; 1x DN50mm inlet; 1x DN65mm outlet |
Manufacturer: | ~ |
Brand: | ~ |
Width: | ~mm |
Manufacturer: | ~ |
Type/number: | ~ |
Manufacturer: | ~ |
Type/number: | ~ |
Manufacturer: | ~ |
Type/number: | ~ |
Manufacturer: | ~ |
Type/number: | ~ |
Manufacturer: | ~ |
Location: | ~ |
Size: | ~ |
Layers/thickness: | ~ |
Fire resistance rating: | ~ |